We are renovating for you: Our hotel will be closed from November 9, 2026 until approximately February 2027. Our new treetop spa will reopen in March 2027. Learn more →

Support

Interessante Baumaterialien

New supports are being concreted onto the outside of the facade.

roof overhang

Hubsteiger im Wald Hotel Heppe zum Dachabbruch

The roof overhang must be removed everywhere so that the balconies can be attached.

The kitchen was quickly dismantled

Küche im Waldhotel Heppe wird demontiert

The kitchen furniture was dismantled within a day; the extractor hood was difficult, but with our partner Gastro Total we managed everything.

It begins

Baustelle früh am Morgen mit Eisenlieferung

On Monday, November 9th, we will start work with several companies at 5 different locations. The shell construction will begin with the concreting of the supports for the next floor, the kitchen will be demolished, the swimming pool ventilation system will be dismantled, the roof overhang will be cut off, and the balconies will be removed.

Waldhotel Heppe · Surrounded by nature

Heppe 1 · 63874 Dammbach
06092 941-0 · info@waldhotelheppe.de

Book now