Accessible toilet completed

PUK Konzept completed the work ahead of schedule – thank you very much! We are delighted to now be able to offer our guests a ground-level washroom compliant with DIN 18040-1.
Final sprint to the toilet
Today, sinks, radiators, changing table, urinal, toilet and grab bars were installed.
The tiles are in.
The tiler will finish today.
Refill
The important foundation is dry, the supports have turned out well, a basement room is almost finished, and the excavators are filling it in again.
Painted – tiling will begin soon.
The new accessible toilet is ready for the tile layers.
The formwork is in place
Everything is prepared for the walls – work continues next week.
Foundation poured

Clean work: The elongated, important foundation on the ground worked wonderfully, and the floor slab of a basement room also fits perfectly.
Big day: The baskets are in!
The metal baskets for the important bottom foundation have been placed.
The first concrete
The first batch of concrete is delivered and poured.
Lowest point reached
We have reached the lowest point of the excavation. Concreting will begin soon.