Initial installations
The stud walls are in place on the side of the new washroom, and the first installations are being carried out.
A major setback: water damage
We suffered a major setback on November 25, 2025: water damage affected our existing residents' dining room and the entire lower floor.
Breakthrough in the outer wall
A new door was cut through the outer wall of the restaurant.
Reinforcement for the foundations
Even in freezing temperatures, the workers tirelessly bend iron for the metal cages of the foundations.
The excavators roll in
Excavation work begins in the backyard. To create the foundation, the supports for the future large extension, and the base slab, several old pipes need to be relocated.
Initial demolition work
Ceiling in the restaurant: An accessible toilet is being built between our two restaurants.
It's starting: The crane is being assembled.
On November 17, 2025, we started work by setting up the crane.